ARMSTRONG HILLS SUBDIVISION

Lake Clifton

Project involved provision of civil engineering services to design 540m of rural road construction, deal with stormwater drainage generated by the development via means of roadside swale drains and site infiltration, as well as provision of an appropriate intersection treatment.


Due to sight distance issues off the main access road, the intersection alignment was modified to provide a safer outcome.
Suitable pavement composition, sealing and turning treatments were negotiated and discussed with Shire of Waroona to meet local requirements, whilst remaining affordable to the client.

Project Summary

Commenced:

March 2015

Completed:

Nov 2017

 Sept 

Services Provided:

Civil engineering